Our Projects

KEPPEL SEGGERS PROJECT

Main Contractor : CYCLECT

Location : TUAS

Job Done : Instrumentation (installation works)

Job Duration : July 08 – May 09

Main cable ladder and branch out cable tray for all the instruments. All the multi core and multi pair cable laying.

View Project Gallery

SHELL MEG PROJECT

Main Contractor : AIR LIQUID (CYCLECT)

Location : Jurong island

Job Done : Instrumentations & Electrical

Job Duration : Dec 08 – Sep 09

Main cable ladder and branch out cable tray for all the instruments. All the multi core and multi pair cable laying and terminations. All the instruments install and run the SS Tubings.
All the sub main cable laying and terminations. Plant lighting, equipment bounding systems, lightning protections system.

View Project Gallery

BAXTER PROJECT

Main Contractor : Siemens

Location : Woodlands

Job Done : Cleaning Room Instrumentation

Job Duration : May 10 – Feb 11

Cleaning room installation, Wire mesh installation. Cable laying, PU tubing, Panel installation, Instrumentation, TIC welding, Glanding termination, MCT installation.

View Project Gallery

EXXON MOBILE (JSS PROJECT)

Main Contractor : Simon Corporation

Location : 35 Pioneer Road

Job Done : Electrical & Instrumentations

Job Duration : Jul 10 – Sep 11

Complete support system works, electrical and instrumentation. HT cable laying LV cable laying, LV panel installation, Instrument installation, SS Tubing, Plant lighting, Earthing system, Heat tracing  all the termination works.

View Project Gallery

SHELL WOODLANDS PROJECT

Main Contractor : CYCLECT

Location : Woodlands

Job Done : Instrumentations & Electrical

Job Duration : Apr 11 – Aug 11

Main cable ladder and branch out cable tray for all the instruments. Complete sub cable laying and termination. Plant lighting, equipment bonding system. All the multi core and multi pair cable laying and terminations. All the instruments install and run the SS Tubings.

View Project Gallery

SENOKO (KEPPEL SEGHERS PROJECT)

Main Contractor : CYCLECT

Location : Senoko

Job Done : Instrumentations & Electrical

Job Duration : Aug 11 – Mar 12

Main cable ladder and branch out cable tray for all the instruments. All the multi core and multi pair cable laying and terminations. All the instruments install and run the SS Tubings.

View Project Gallery

BOUSTEAD PROJECT

Main Contractor : CYCLECT

Location : Jurong Island

Job Done : Electrical Instrument Project

Job Duration : Sep 11 – Jun 12

MCC & PLC panel Installation, cable tray and trunking installation and cable laying, Instrument installation, termination and testing

View Project Gallery

PROJECT IN Power Plant – GMR Energy 2x400 MW CCP Project

Main Contractor : CITIC (GMR)

Location : Jurong Island

Job Done : Instrumentation Project

Job Duration : October 2012 – July 2013

All the Instrument Installations. All the support system including cable laying and termination. Install Impulse Line (SS Tubing)

View Project Gallery
Showing 1 to 8 of 11 entries